Kinetiko Energy Ltd. is making key strides toward commercialising its shallow conventional gas assets in South Africa, advancing both regulatory permitting and infrastructure development at its Brakfontein project.
The company is preparing to lodge its Bulk Sampling Permit (BSP) application with the Petroleum Agency of South Africa (PASA) by late October. Expected to be granted in the first quarter of 2027, the permit will allow Kinetiko to produce and commercialise early gas volumes while broader regulatory approvals progress.
In tandem, Kinetiko is preparing a comprehensive production right application (PRA), covering Exploration Right 271 (ER271) to underpin its broader Rolling Cluster Development Strategy.
An Environmental Impact Assessment (EIA) to support the application is underway, following the recent completion of initial water monitoring well drilling.
On the development front, detailed engineering works are progressing for the Brakfontein Phase 1 Cluster. The design involves connecting existing wells to a central manifold and a mobile, modular Compressed Natural Gas (CNG) facility.
A preferred supplier for the CNG unit has been shortlisted, with contract award and front-end engineering set for the fourth quarter of 2026.
Subsurface modelling has also narrowed down three shortlisted sites for the company’s next well (Cluster 2), with drilling scheduled to commence in early 2027 following the delivery of long-lead items in February.
“Kinetiko is making steady progress across each of the workstreams needed to take Brakfontein from exploration to production,” said Executive Chairman Adam Sierakowski.
“Submitting the Bulk Sampling Permit application is a key step on our pathway to first gas, as it allows us to produce and sell limited volumes of gas while we progress the Production Right.”
To lead the company’s transition from explorer to producer, Kinetiko has completed candidate shortlisting for a new CEO. The company has shortlisted three candidates and expects to complete the selection process in October.
Meanwhile, commercial negotiations for land access compensation with local renewable energy developers continue to progress.